Smaller frames are installed next to the last wider frames. The smaller frames are attached to the back of the larger frames on either side.

The last garage frame is installed and attached to the top of the garage header which allows for garage doors that are wider than the frame spacing.

Close-up of the garage I-beam header installed between the outside garage frames to allow for the garage door openings. The header allows shortened columns to sit on top instead of going all the way to the foundation. Headers are used when an opening for a door or window falls where a column would normally be located.

All the frames are erected and the roof purlins have been installed. The workers at the back corner are just starting to install the roof sheathing. Note that the cross braces and lateral braces will be left in place until the roof has been sheathed.
|