about ESS
steel is better
the ESS difference
whats included in our package
buildingprocess
freqeuntly asked questions
house plans
examples of custom homes
Excalibur Steel Structures Logo
photo gallery
glossary
visit our net forum
free estimate
free literature
join ESS team
builders and framers
links


Customer Photo Journal

Basement
1st floor

Notes from Excalibur:
1) Text has been condensed for clarity;
2) Steel may look bowed, this is due to      customer's "wide angle lens."



Foundation Steel Finishing
A B C 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

December 12, 2004

 

I thought when I got to this stage of completion I would have more time to take care of these updates.  WRONG!!!!!  I have been covered up the past few weeks with doing, helping do and getting materials for everyone else.  Anyway, much has happened in the past seven weeks.

 

 

One of the things shown in the last update was the crown molding installation.  The picture below shows a good close-up of the finished job with two coats of paint and the walls painted.  This is the family room and the room in the background is the sewing room.  Remember from the last update that the molding was actually a cove design and the inside corners were coped and not mitered.  We have had many good comments on the finished job on the crown.


cf14c0.jpg

 


All of the trim on the first floor, including the baseboard, windows, door casing and doors on the first floor are complete.  Joel still has to do some base, the two windows in the basement and the stairs before he finishes painting in the basement.
 

 


Abb, who has consulted and tutored me with all of the details of the house, had a special way to install the stairs for both an appearance and structural standpoint.  A piece of ½” plywood was put up before the stringer was put in place.  The risers are primed and then put in place being sure to keep them level side to side.  The skirt board is then installed on each side.  The riser is plumber upward and the tread outward to give the outline of the stair case on the skirt board.  The skirt board is then cut and it will now drop down into place fitting the riser and stringer level of the tread.  The risers are shimmed out as necessary to make them match the plumb line cut from the layout.  The treads are then cut to fit in with a very tight fit and then fastened in place.  The back of the riser is then fastened into the tread to firmly attach it in place.  In this case, we screwed the tread down and then plugged the holes with walnut plugs.  The picture below shows the finished product of the stairs from the landing up to the first floor.


cf1665.jpg

 

 


The picture below shows the stairs from the basement floor to the landing.


cf166f.jpg

 

 


Another big thing to do in the past few weeks is get the form ready to pour the concrete.  As soon as we did, the weather turned bad and we have only been able to pour half of the slabs.  It is to be sunny this week, but cold at night (down into the 20’s) so I am hoping we can finish the concrete tomorrow.  The backyard area is still muddy, but maybe they can get the truck in and out.  The picture below shows the front parking area.  It is wide enough to hold two cars.  The gravel area towards the front porch will be the front sidewalk.  This concrete will be colored to a slate gray and will have saw cuts to give a design.  The front porch will also be colored the same and have the same pattern cut into it.


cf1679.jpg

 

 

The picture below is the parking area outside the garage with the walk to the door to the garage and back porch on the left.  The step from the garage level to the back porch will have a landing that will have the same colored concrete and pattern cut to match the front and back porch.  This was taken before the garage was poured.


cf1683.jpg

 


The forms below show the slab area for the back yard.  There will be a slab out from the French doors with a sidewalk over to a slab in front of the garage door.  The concrete will go up and wrap around the slab the HVAC compressors are sitting on.  This slab will be the slate grey, but without any saw cuts.


cf1697.jpg

 


The HVAC units are complete and working now.  We needed the heat in the house for painting.  The units are Amana with a 16 SEER rating.  They have a life-time warranty on the compressors.  Both are two-stage, with the basement unit having a 2/3 ton rating and the first floor a 3/5 ton rating.  Both air handlers have a DC fan motor for variable speed control.  You can barely hear the unit in the basement running and cannot hear the unit on the first floor when they are running.  They units still have to be balanced from room to room.  Dampers were installed in all of the duct work to each register.


cf16a1.jpg
 

 


The septic tank system has been installed now and ready to use.  With the type of soil on the property, we had to install an anaerobic and aerobic unit plus an effluent tank to pump up to the drain field.  The county almost made me put in a drip system that would have been double the cost of what we have.  The picture below shows the line up of the tanks.  The first tank is the anaerobic tank, the middle the aerobic and the third tank the effluent tank.  The pipe to the field line had not been installed when this picture was taken.  The three tanks are parallel to the wall on the south side of the back yard.


cf16ab.jpg

 

 


Of course with a system like this you need controls.  This picture shows the power mounted on the retaining wall to the right of the HVAC units.  The distribution panel in mounted on an aluminum plate.  The top red light is an alarm for the air not going to the aerobic tank and the lower red light is the alarm for high level on the effluent tank.  The air compressor for the aerobic tank is at the bottom of the picture.


cf16b5.jpg

 

 


Just about all of the plumbing in the house is complete.  All of the toilers are set and most of the faucets are installed.  The water heater is set and the pressure tank connected.  A little work is needed to finish this.

 


The cabinets for the kitchen are now set.   The picture below is from the family room into the kitchen.  For reference, the double oven cabinet is right behind the saw.


cf16bf.jpg

 

 


This is the wall on the right walking through the kitchen from the rear entry to the family room.  The double oven is in the big cabinet and the refrigerator is in the opening at the right.


cf16c9.jpg

 

 


The picture below shows the cabinets from the front of refrigerator with the family room back to the right.


cf16d3.jpg

 

 


We are still waiting for the doors and island to be delivered this week.  The top will be set this coming Wednesday the 15th.  The island is 42” x 101” and will have a granite top on it.  It will sit centered of the room and will still have 3 ½’ to 4’ of walk space around it.  The doors will look like the game room kitchen shown below.  The counter top will be the same design in the main kitchen.  It is seamless man-made marble.


cf16dd.jpg

 

 


The master bath shower and tub surround has been finished.  The glass shower enclosure and mirror will be set this week.  The picture below shows the status today.


cf16e7.jpg

 


A French drain has been installed in the back yard to help keep the water out of the area.  Also all of the downspouts are run underground to a drain to keep the water away from the house.


cf16f1.jpg


 


The insulation has been put in the attic.  It was blown in and has an R-30 value to match the insulation in the walls.


cf16fb.jpg

 


That about wraps up what I have done for the past seven weeks.  This week I hope to get the concrete poured, kitchen counter top set, glass doors to shower installed, mirrors for all baths installed, the painting just about completed and the columns enclosed for both of the porches.

I will try to give you an update right after the first of the year.



back         next



about ESS
steel is better
the ESS difference
whats included in our package
buildingprocess
freqeuntly asked questions
house plans
examples of custom homes
Excalibur Steel Structures Home Page
photo gallery
glossary
visit our net forum
free estimate
free literature
join ESS team
builders and framers
links

Excalibur Steel Structures
Copyright© 1997 - 2006 All Rights Reserved.
E-Mail: info@ExcaliburSteel.com