|
July 29, 2004
And there they go!

The HDC Construction crew that is. The have finished up
all that they can do for me and are heading home. Their last visit has been for
16 days and I will walk you through what we have done in this report.
All of the electrical has been completed. This area was where I made my biggest
mistake on the project. I was planning on doing all of the internal wiring by
myself. BIG MISTAKE!!! I was able to get up about 85% of the boxes for the
receptacles and switches. They put up the rest of the boxes and then pulled all
of the wire for power, telephone, data and video. They were good and they were
fast. As I have mentioned before Murray Hughes, the owner of HDC, and one of
his workers are IBEW Journeyman Electricians. They have worked large jobs
including nuclear plants during their career. They have also wired many steel
frame homes and know all of the secrets. They kept me busy just keeping them
material.
The picture below is the two incoming lighting panels. The
panel to the left is all of the lighting and receptacles and the downstairs HVAC
unit that hopefully one day will be fed from a standby generator when the power
is interrupted. The automatic transfer switch is all ready in place. The panel
to the right has all of the cook tops, ovens, and ranges, dryer and other
circuits that can be interrupted.

The picture below shows how they dressed the wire in going from one box to
another. Note how the wiring is taken through grommets in the studs, secured to
the studs and then shaped when bends are necessary. They installed about 10,000
feet of power cable for feeders, lights, receptacles and appliances, 4,000 feet
of Cat 5 cable for telephone and data and 2000 feet of video cable. This does
not count the security wiring and sound system.

The brick could not be placed until the frieze board, soffits and fascia were
installed. HDC did that work also. The picture below shows across the front of
the house including the front porch. All of the frieze board and fascia is vinyl
covered aluminum and the soffits material is ventilated PVC. A beam had to be
built down from the ceiling on both of the porches to tie the frieze boards into
the porch area. The steel columns on the porch will be encased in 16 inch
square columns. Another column will be to the left and right of the steel
covered columns to give four columns across the front of the porch. In the
picture, note the porch foundation comes out past the front of the column so
that a brick planter may be placed for decoration. Also note, that the corners
are mitered at a 45 to really dress out the soffits

The picture below shows the transfer from the three foot
overhang to the seven foot overhang on the back of the house. This picture also
shows a good picture of the frieze board. For those who do not know what it is,
this is a good place to discuss it. The frieze board runs [horizontally under
the soffit, and is placed] about 4 ¼” away from the wall. A string was placed
in each inside and outside corner of the frieze board. The masons will then use
a plumb-bob to locate the place of the footers to start the brick work for each
corner. Using this line to build up the wall, they will then meet under the
frieze board. The last course above the window height will be a “soldier
course” of bricks used to top out the wall. It is called a “soldier course”
because all of the bricks are standing up on end. This makes it easier for the
mason to place them [behind the frieze board].

The front door was received while they were here and they placed it yesterday.
Below is a picture of it in place. Brick work will have to be done to bring the
porch floor up the proper level. The finished porch floor will be about the
height of the lower edge of the aluminum tape sealing the door. The upper boxes
on the wall are for light sconces and the lower two boxes are for electrical
outlets.

The plumbing should be finished up today. The insulators have been notified
that they can start on Monday for their work. I need to put in some blocking
for pictures, drapery rods, toilet paper holders, handicap bars, etc. before the
sheetrock can be placed. I will be working on that now through next week and
hopefully I will be ready as soon as the insulation is complete.
|